Below is a checklist of key aspects to inspect during and after the completion of asphalt concrete paving:
- Surface Quality
Smoothness: Check for surface irregularities such as bumps, dips, or depressions using a straightedge or a profilometer.
Evenness: Ensure the surface is uniform with no visible segregation, streaking, or surface tearing.
Texture: Verify the pavement has a consistent surface texture suitable for skid resistance.
- Thickness
Core Samples: Take core samples to measure the actual thickness of the asphalt layers and compare them to the design specifications.
Depth Verification: Confirm that each lift of asphalt meets the required compacted thickness.
- Density and Compaction
Compaction Testing: Use a nuclear density gauge or other approved methods to verify that the asphalt has been compacted to the required density (usually 92-96% of maximum theoretical density).
Joint Density: Pay special attention to longitudinal and transverse joints, ensuring proper compaction to prevent future cracking or separation.
- Gradation and Mix Compliance
Asphalt Mix: Verify that the asphalt mix used matches the approved mix design.
Aggregate Gradation: Confirm the size and distribution of aggregates are within the specified tolerances.
Binder Content: Check that the asphalt binder content meets the project requirements.
- Temperature Control
Paving Temperature: Ensure the asphalt was placed within the specified temperature range (typically 275–300°F for hot mix asphalt). etconp
Compaction Temperature: Confirm compaction was completed before the asphalt cooled below the recommended temperature for proper bonding.
- Joints
Alignment: Check that joints are straight and aligned properly with adjacent lanes.
Bonding: Inspect the bonding at longitudinal and transverse joints for gaps or loose edges.
Sealing (if required): Verify that joints have been sealed with the appropriate material to prevent water infiltration.
- Drainage
Grade and Slope: Ensure the pavement is graded to allow for proper drainage, avoiding areas where water could pond.
Catch Basins and Inlets: Verify that drainage structures are clean, properly aligned, and free of obstructions.
- Edges and Shoulders
Edge Alignment: Inspect the edges for straightness and uniformity. etconp
Shoulder Material: Ensure shoulders are compacted and smoothly transition to the asphalt pavement.
- Markings and Signage
Pavement Markings: Confirm that lane markings, crosswalks, and other painted symbols are applied according to specifications and are properly aligned.
Reflectivity: Check that reflective beads are embedded in markings, where required, for nighttime visibility
- Documentation
Test Records: Review all quality control and quality assurance test results, including compaction, density, and asphalt mix compliance.
Inspection Reports: Ensure all stages of work have been inspected and approved.
Punch List: Address any outstanding issues or deficiencies noted during the inspection etconp
- Final Approval
Walkthrough Inspection: Conduct a final walkthrough with project stakeholders (contractor, inspector, and owner) to confirm all work meets contractual requirements.
Acceptance Certificate: Obtain written approval or a certificate of acceptance from the relevant authority.
By systematically inspecting these aspects, you ensure the asphalt pavement is constructed to high standards and will perform effectively over its design life.